October – December 2008: Background research and project establishment phase
-
February – May 2009: ‘Vision’ workshops and meetings with Council groupings, and initiate contact with key takeholders to gauge issues and assist with determining the focus of the review process
-
May – July 2009: Undertake a series of plan topic reviews, collating the outcomes of the above work, establishing the issues, priorities and options for the review, and determining the broad structure and format for the District Plan. Concludes with seeking Council endorsement for outcomes identified, and for the ongoing work programme and timeframes
-
July 2009 – September 2010: Prepare issues papers on the six (approximately) key issues for the District
-
July 2010 – March 2011: Assemble a draft District Plan for stakeholder and public comment
-
March – August 2011: Consultation period on draft district Plan
-
September – December 2011: Review feedback received, undertake revisions as needed and present to Council for endorsement to enable public notification as a Proposed District Plan
-
April 2012: Publicly notify the Proposed District Plan and call for public submissions pursuant to the statutory Resource Management Act process
-
May – August 2012: Summarise public submissions received and notify the summary calling for further submissions, pursuant to the Resource Management Act process
-
September – December 2012: Work through issues raised in submissions, identify if any further background study needed to fill information gaps, and prepare the hearing report
-
February – May 2013: Conduct hearings
-
June – August 2013: Council releases decisions on public submission